ICS 27.100
P 60
Record No. J181—2002
Electric Power Industry Standard of the People's Republic of China
P DL / T 5159 — 2002
Technical Code for Geophysical
Exploration Electric
Power Engineering
Transmission Lines
Issue Date: April 27, 2002 implementation Date: September 1, 2002
Issued by the State Economic and Trade Commission of the People's Republic of China
1 Scope
This code specifies the technical methods, requirements,measurements, data analysis and interpretation methods for engineering geophysical exploration, and is applicable to newly built or expanded fossil fuel power plants, nuclear power plants,substations, overhead transmission lines, and planning of electric power systems. This code may be taken as a reference for other types of geophysical exploration activities.
2 Normative References
The following normative documents contain provisions which, through reference in this text, constitute the provisions of this code.
For dated references, subsequent amendments (excluding the contents of errata) to, or revision of, any of these publications do not apply.
However, parties to agreements based on this code are encouraged to investigate the possibility of applying the most recent editions of the normative documents indicated below. For undated references, the latest edition of the normative documents apply.
GB/T 50269—1997 Code for Measurement Method of Dynamic Properties of Subsoil
DL 5001—1991 Technical Code for Engineering Survey of Fossil Fuel Power Plants
DL 5010—1992 Code for Engineering Geophysical Exploration Hydropower and Water Resources
DL/T 5156.5—2002 Electric Power Engineering Surveying Drawings Part 5: Geophysical Prospecting
CJJ 61—1994 Technical Specification for Detecting and Surveying of Underground Pipelines and Cables in City
JGJ/T 93—1995 Specification for Low Strain Dynamic Testing of Piles
JGJ 106—1997 Specification for High Strain Dynamic Testing of Piles
JGJ 944—1994 Technical Code for Building Pile Foundation
3 General Provisions
3.0.1 The geophysical exploration used in hydrogeological and geotechnical investigation for electric power construction purposes is collectively called electric power engineering geophysical exploration (hereinafter referred to as geophysical exploration). Nowadays commonly used methods include electrical method, seismic method, well logging method, rock-soil in-situ test, non destructive testing of piles, underground pipelines and cables detection technology, radon detection technology, sonic test technology, and Rayleigh wave test technology.
3.0.2 Geophysical exploration is an important means of geological exploration, ground treatment, and quality examination. Its proper use in conjunction with electric power surveying and design characteristics may help improve the surveying quality, shorten the time, and reduce the cost.
3.0.3 Geophysical exploration must be carried out in close conjunction with geological survey. Attention is drawn to tests and determination of various physical parameters of rock and soil, which shall be utilized in an extensive manner to overcome the limitations of a single method in conditional use and multiple interpretations, and obtain correct conclusions.
3.0.4 New geophysical exploration technologies shall be actively used and promoted. Attention is to be given to the verification of geophysical exploration results and the return visit for geologic effects.
3.0.5 In electric power engineering, the geophysical exploration work processes are generally as follows: acceptance of task; data collection; reconnaissance survey; plan preparation; method testing;field work; data organization; submission of results. The above processes may be streamlined under special circumstances.