安全生产隐患识别口袋书2020(上篇)
附件大小:68.21MB附件格式:2个直链文件,格式为pdf pptx
所属分类:安全文明
分享会员:芳华
分享时间:2022-08-05
最后更新:
资源简介/截图:
目录
第一章:文明施工··························································································································· 1
第二章:基坑工程························································································································· 22
第三章:脚手架工程······················································································································ 35
第四章:模板工程························································································································· 67
第五章:高处作业························································································································· 98
第六章:施工消防························································································································ 137
第七章:施工用电························································································································ 149
第八章:施工机具························································································································ 174
第九章:施工电梯························································································································ 185
第十章:塔式起重机····················································································································· 215
第十一章:起重吊装····················································································································· 240
第十二章:吊篮作业····················································································································· 269
第十三章:钢结构工程·················································································································· 290
第十四章:机电安装····················································································································· 322
第十五章:中型设备····················································································································· 336
第十六章:道路工程····················································································································· 353
第十七章:桥梁工程····················································································································· 374
第十八章:隧道工程····················································································································· 420
第十九章:其他··························································································································· 476
内容摘要:
问题描述:
①施工现场未实行封闭管理;
②施工现场大门未设置企业 CI 标识。
整改措施:
①施工现场安装企业大门及门禁系统,严格执行封闭管理;
②施工现场大门设置企业 CI 标识。
原因分析:
①施工现场管理标准低,临时设施费用、安全文明施工费 用投入不足;
②防偷防盗措施落实不到位。
管控措施:
①提高施工现场管理标准,保证临时设施费用、安全文明 施工费用投入到位;
②加强施工现场安全保卫工作,落实防偷防盗措 施。
隐患描述:
①围挡封闭不严,未实现现场全封闭;
②围挡未设置警示灯、企业 CI 或安全标牌标语等;
③围挡基础不稳固,固定方式不牢靠。
整改措施:
①对所有破损、开口处重新设置全封闭围挡,确保满足高度要求;
②在转角、主要道路路段等区域加设警示灯,设置企业 CI 或安全标牌标语等;
③优先选用彩钢板、砌体等硬质材料设置围挡;
④加固围挡基础,加强日常巡查检查。
原因分析:
①安全费用投入不足,围挡选型、材质标准低、质量差;
②基础和支撑方式设置稳定性差;
③围挡设置后,项目管理人员日常巡查检查不足。
管控措施:
①合理设计、设置围挡,保证安全费用投入,必须符合属地要求,展示企业形象;
②围挡安装过程中加强监管,安装完成后验收合格方可投入使用;
③项目管理人员加强对围挡设施的检查和维修。