2011年12月上 施工技术 第40卷第354期 CONSTRUCTION TECHNOLOGY 桃园1号隧道施工监测技术 靳子良,周建春 (华南理工大学土木与交通学院广东广州510640) 摘要]在桃园1号隧道工程施工过程中,通过现场监控来掌握隧道围岩与支护结构的工作状况和安全信息及时 预见险情,为调整和修改支护设计参数以及改变施工方法提供重要的依据,从而保证施工安全和降低工程造价。 主要从地表沉降、拱顶下沉和周边收敛、钢支撑内力、二次衬砌的应力等几个方面对监控量测的实施与分析进行了 介绍。 关键词】隧道工程;监测沉降;收敛;内力 中分类号】U456.3 [文献标识码]A [文章编号]1002-8498(2011)23-0053-04 Construction Monitoring Technology in Taoyuan No .1 Tunnel Jin Ziliang ,Zhou Jianchun ( Schoolof Engineering and Transportation ,South China Uninersity Technology ,Guangzhou Guangdong 510640 ,China ) Abstract :In construction of Taoyuan No .tunnel ,the authors master work conditions and safety information of surrounding rock and support structure based on site monitoring to provide reference for adjusting and modifying support parameters in order to ensure construction safety and reduce the cost . Implementation and analysis of monitoring are introduced in detail from ground settlement ,vault crown settlement ,peripheral convergence ,internal force steel support and stress of the secondary lining . Key words :tunnels ;monitoring settlement ;convergence internal force 在隧道施工过程中遇到的地质条件复杂,地下 211.2m,所经地区为粤中地块,地震基本烈度为6 水和围岩压力等作用下的荷载是不明确的,目前对 度,在设计中按7度设防。隧道区洞身岩石厚度...