2010年2月 施工技术 第39卷第2期 CONSTRUCTION TECHNOLOGY 93 沈阳东北世贸广场塔式起重机的选用 张永林,张喜 (北京怀建集团有限公司,北京101400) [摘要]沈阳东北世贸广场超高层结构工程施工中,塔式起重机是大型机械设备.通过对市场的调查及结合本工 程实际情况,制定了塔式起重机安装、拆除方案及各项安全管理措施,闸述了塔式起重机,特别是内爬式塔式起重 机的平面布置、型号选择、安装、爬升及拆除,使其安全运行,确保超高层结构工程的顺利施工. [关键词]沈阳东北世贸广场;高层建筑;内爬塔式起重机;安装;爬升;拆除 [中图分类号]TH2 [文献标识码]A[文章编号]1002-8498(2010)02-0093-03 Selection of Tower Crane in Shenyang Northeast World Trade Plaza Zhang Yonglin Zhang Xi (Beijing Huajian Group Co.Ltd.Beijing 101400 China) Abstract:During the construction of super high-rise structure in Shenyang Northeast World Trade Plaza the tower crane is a kind of large-scale mechanical device.Based on the market survey and actual situation the plans of installation and demolition for the tower crane and safety control measures are made.Besides the plane layout model choice installation climbing and demolition of the tower crane are elaborated especially the inner-crawling tower crane.Safety operating of the tower crane can guarantee the smoothy construction of the super high-rise structure. Key words:Shenyang Northeast World Trade Plaza;high-rise building;inner-crawling tower crane; installation;climbing;demolition 1工程概况 心筒组成,58~63层内简为钢筋混凝土核心筒及四周 沈阳东北世贸广场(见图1)位于沈阳市北站经济为轻钢组成的混合结构. 开发区,占地面积约3万m2 总建筑面积35万m2 其 中主楼建筑面积为12.39万m3.本工程由1栋260m 高的63层主楼、2栋100m高的27层辅楼和35m高的 7层裙房组成. 由于建筑施工条件复杂多变,主要从以下方面考 虑:建筑物体形、结构和平面配置;建筑层数、层高、基 础标高及建筑总高度;建筑工程实物量、材料设各搬运 量;构件制品、单个构件重量、安装位置及其形状;工 期、施工节奏、施工流水段的划分及施工进度安排;建 筑基础及周围施工环境条件;本地区供应条件;本单位 的资金情况以及对经济效益的要求等. 图1沈阳东北世贸广场示意 工程主...