施工技术 2014年8月上 10 CONSTRUCTION TECHNOLOGY 第43卷第15期 D01:10.7672/sgjs2014150010 沈阳惠生新城项目装配式构件关键技术 张建国,张超,于奇 (亚泰集团沈阳现代建筑工业有限公司,辽宁沈阳110136) [摘要]沈阳惠生新城公租房项目1~30号楼采用装配式剪力墙结构,为目前国内采用装配整体式剪力墙体系工 程量较大的项目之一,其预制构件设计、生产、运输、安装、验收等较困难.结合该项目,介绍了装配整体式结构拆 分设计、构件生产、选用及安装质量控制要点. [关键词]装配式建筑;设计;生产工艺:模具;质量控制 [中图分类号]TU758.12 [文献标识码]A [文章编号]1002-8498(2014)15-0010-06 Key Technology of Prefabricated Members in Shenyang Huisheng New City Project Zhang Jianguo Zhang Chao Yu Qi (Yatai Group Shenyang Modern Building Industry Co.Ld.Shenyang Liaoning 110136 China) Abstract:Prefabricated shear wall structure is adopted in Shenyang Huisheng New City project which is the prefabricated shear wall structures with large amount of engineering quantity in China.So the design production transportation installation and acceptance of its prefabricated members are difficult.Based on the project the keys for split design of prefabricated structure member production selection and installation quality control are introduced. Key words:prefabricated;design;production;moulding;quality control 沈阳市从政府项目入手扩展应用领域.按照和休息平台板、电梯间以及局部出屋面电梯及装饰 强制推进和引导激励相结合的原则,首先从政府投架为全部现浇结构. 资的保障房项目入手,通过实践,在不断完善技术 惠生公共租赁住房工程标准层为一梯八户(4 和管理体系的基础上,以政策引导房地产项目应用 个A户型、2个B户型、1个C户型、1个D户型)拆 现代建筑产业化技术.惠生公租房项目就是在政 分成20块外墙板、18块内墙板、22块叠合板、6块 策引导下应运而生.本文将介绍惠生项目装配式 PCF板、2块楼梯板、10块空调板. 构件设计制作及安装质量控制要点,以期为类似工 模具数量依据惠生项目的施工建设工期进行 程提供借鉴. 排班,每天按照生产3层楼的产量进行模具采购, 1工程概况 模具总数量为246套,其中,外墙板62套、内墙板 本工程为沈阳市产业化公共租赁住房工程,项 54套、叠合板66套、楼梯板6套、PCF板18套、空 目名称为惠生新城(公租房)1~30号楼;位于沈阳 调板30套以及...