施工技术 2017年7月上 72 CONSTRUCTION TECHNOLOGY 第46卷第13期 D0I:10.7672/8js2017130072 深大基坑咬合桩支护结构数值模拟研究 陈秀辉1 2 (1.福建省建筑科学研究院,福建福州350025;2.福建省绿色建筑技术重点实验室,福建福州350025) [摘要]以襄阳新天地基坑工程为对象,采用有限元分析软件ABAQUS对该基坑支护结构的变形过程进行数值模 拟,并与监测结果进行对比分析,得出模型建立是合理可行的.采用所建立的模型讨论了桩长、桩径、错索预应力 的设置对基坑变形的影响,并得出了规律性的结论. [关键词]深基坑;支护;桩;钻孔咬合桩;数值模拟;变形 [中图分类号]TU753 [文献标识码]A [文章编号]1002-8498(2017)13-0072-05 Numerical Simulation of Secant Pile Support Structure in Deep Foundation Excavation CHEN Xiuhui.2 (1.Fujian Academy of Building Research Fuzhou Fujian 350025 China;2.Key Laboratory of Fujian Green Building Technology Fuzhou Fujian 350025 China) Abstract:This paper used ABAQUS finite element analysis software to simulate deformation of a foundation excavation in Xiangyang.Compared with the monitoring data the model establish is reasonable and feasible.The pile length pile diameter and the prestressed anchor cable effect on the deformation were diseussed and the regularity conclusion was obtained. Key words:deep foundation excavation;supports;piles;secant pile;simulation;deformation 1工程概况 62.330m.各土层中粉质黏土与粉土透水性弱,粉 襄阳新天地项目位于襄阳市樊城区解放路一砂与圆砾具有强透水性,泥岩为隔水层.所以本工 桥桥头东北方位,占地面积5万m2 地上总建筑面程必须考虑地下水对基坑开挖的影响. 积17.1万m2 地下总建筑面积2万m2.共布设63施工工艺及协调变形 幢高层建筑物(其中4幢45层,2幢42层),6幢多 3.1施工工艺 层建筑物(商铺及幼儿园).高层建筑物下设3层 施工中一般采用全套管钻机进行施工,这种基 整体地下室,基础埋置深度为14.0m 采用桩筏基 坑围护结构的特点就是桩与桩之间形成相互咬合 础,基础桩采用旋挖成孔钻孔灌注桩. 排列形式.该工程咬合桩由钢筋混凝土桩(A桩) 2工程地质条件 和素混凝土桩(B桩)组成,A B桩间隔布设,一般 场地地面标高66.010~70.230m 相对高差约 先施作素混凝土桩后施作钢筋混凝土桩,B桩中的 4.12m 属汉江一级阶地.根据区域资料,场区范围 混凝土在初凝之前必须有足够的时间完成A桩...