2014年7月上 施工技术 第43卷第13期 CONSTRUCTIONTECHNOLOCY 133 DOI;10.7672/sgjs2014130133 厦门世侨中心地下室钢结构逆作法施工技术 唐香君,周仲强,商洪军,李庆斌,秦益军,徐雷 (江苏沪宁钢机股份有限公司,江苏宜兴214231) [摘要]厦门世侨中心项目场地狭小,施工条件有限,按常规的施工次序难以施工。
为保证项目施工进度,采用“逆 作法”施工,在深井孔桩中预理钢管柱作为逆作施工的支撑承重,自上向下逐层进行钢结构施工。
实践表明,地下 室钢结构采用“逆作法”施工,仅用4个月时间即完成了主体钢结构的封顶,减少了人力投人,节约了施工成本。
[关键词]地下工程;钢结构;钢管柱;逆作法;施工技术 [中图分类号]TU753 [文献标识码]A [文章编号]1002-8498(2014)13-0133-04 Top-down Construction Technology of Basement Steel StructureinXiamenShiqiao Center TangXiangjun,ZhouZhongqiang,Shang Hongjun,Li Qingbin,QinYijun,XuLei (Jiangsu Huning Steel Mechanism Co.,Ld.,Yixing,Jiangsu 214231,China) Abstract:It's difficult to construct in Xiamen Shiqiao Center by conventional construction sequence because of the narrow field and plicated construction conditions.The top-down method ensures the schedule of construction.The bearing supporting frame must rely on the pre-embedded steel pipe columns in the hole-pile.The structural practice indicates that the main structure pleted by four months. This construction methodreduced the human input and the construction cost. Key words:underground; steel structures; steel tubular column;top-down method;construction 1工程概况 厦门世侨中心项目为高层办公楼,占地面积为 3648.71m²,总建筑面积为45552.6m²,其中地下4 层,面积为10077.6m²,地上共27层,面积为 35475m。
建筑设计使用年限为50年。
建筑大屋面 高度为98.7m,建筑总高为112.3m,如图1所示。
厦门世侨中心地下室为全钢结构,由方钢管混 凝土柱和钢梁、支撑组成。
地下室主要分为地下4 层,包含26根钢管混凝土柱和4层钢梁(含首层)。
钢管柱截面主要采用箱形截面,截面尺寸较大,主 要为口1500×900×35,口1300×800×35,900× 图1厦门世侨中心整体效果 800×35,口1100×800×35。
钢管柱内灌C60混凝 Fig.1Xiamen Shiqiao Center effect 土。
楼层钢梁均为H型钢梁,主要为焊接H型钢 梁,局部次梁为轧制H型钢梁。
2)地下室钢结构逆作法施工在钢管柱深井 2工程难点 孔施工完毕后立即进行锚栓架和定位器的安装,之 1)场地制约因素本工程现场施工场地狭小, 后进行钢管柱的安装;待钢管柱安装至首层楼板结 对本工程钢构件安装制约性较大,因此钢构件必须 构标高以上位置处,进行地下1层以下土方的开挖。
根据现场安装进度有序进场。
地下室钢结构随土方开挖进度从首层往下进行,上 [作者简介]唐香君,助理工程师,项目技术负责人,E-mail:hngjzhglb 部结构继续往上进行,保持上下同时施工,施工顺 163. 序不同于一般工程,整个施工过程中一直在进行地 [收稿日期]2013-07-10 下土方的开挖,地下施工工作面狭窄,构件的吊装 万方数据
134 施工技术 第43卷 运输也比较困难。
对施工单位的技术要求相当高。
: 场进行轴线和标高控制点的复测和加密,形成控制 3)地下室施工安全本工程地处厦门海边,受网。
然后根据控制线测放出每根钢管柱的轴线,标 厦门海水天文...