施工技术 2013年6月下 32 CONSTRUCTION TECHNOLOGY 第42卷第12期 D0I:10.7672/sgjs2013120032 某渠道工程湿陷性黄土基础处理技术 刘雪峰,程文香,王军辉 (武警水电第二总队第五支队,江苏常州213135) [摘要]南水北调某施工标段全长14km 含明渠13km 其中分布湿陷性黄土渠段6.6km.依据不同渠段湿陷性大 小及其周边环境差异,分别采取强夯、重夯、土挤密桩以及扩挖换填等恰当的工程措施后有效地消除了渠基湿陷 性.对该工程基础处理方法进行了背景分析与技术总结. [关键词]基础;湿陷性黄土;处理 [中图分类号]TU753 [文献标识码]A [文章编号]1002-8498(2013)12-0032-04 Treatment for Collapsibility Loess Ground in Some Channel Engineering Liu Xuefeng Cheng Wenxiang Wang Junhui No.5 Detachment No.2 Hydropower Force of Armed Police Changzhou Jiangsu 213135 China) Abstract:One construction segment of South-to-North water transfer project is 14km in length in which the length of open channel is 13km with 6.6km-length collapsible loess channel.Based on difference of collapsibility and surrounding environment some treatment measures are used to eliminate collapsibility of channel foundation such as dynamic paction heavy rammer soil paction pile and enlarge dig in to fill in.This paper analyzes and summarizes the ground treatment method. Key words:foundations;collapsibility loess;treatment 1工程概况 湿陷的两个内部因素,而压力和水是外部条件.地 南水北调中线干线某施工标段全长14km 其中 基处理的目的则是改善土的性质和结构,减小土的 明渠13km 渠道为梯形断面,渠底宽14.5~19m 渠渗水性、压缩性,消除其湿陷性. 道内坡1:2.0~1:2.75,纵比降1/28000,采用渠坡3技术要求 厚10cm 渠底厚8cm的混凝土衬砌,需进行基础处 3.1强夯 理的湿陷性黄土渠段面积44万m2 划分为13个设 处理范围超出渠道外坡脚线3m 分3遍完成, 计段,长6.6km 占明渠总长的51%.湿陷性中等 前2遍为点夯,第3遍满堂夯,每遍10击;前2遍夯 以上的9个设计段,共5.54km 采用强夯法处理,湿 击能2000kNm 锤重20t 锤底面直径2.5m 夯点 陷性轻微的1个设计段,共0.31km 采用重夯法处间距6.5m 落距10m 第1遍夯点正三角形布置,第 理,距离村镇较近的3个设计段,共0.78km 采用土 2遍夯点在第1遍夯点...