施工技术 2015年7月上 60 CONSTRUCTION TECHNOLOGY 第44卷第13期 D01:10.7672/sgis2015130060 深厚砂层及卵砾石层中成槽的TRD工法挖掘液 配制方法与应用 褚立强 (上海智平基工程有限公司,上海200060) [摘要]利用膨润土配制的挖掘液泥浆适用于黏性土、粉质土层中的TRD工法成槽,经过改进后的挖掘液配制方法 更适用于以砂层及卵砾石层为主的地层内成槽施工.结合工程实例,详细介绍了以黏土(颗粒度调整材料)代替膨 润土的挖掘液配制计算方法.实践证明,在TRD工法施工过程中,该种以颗粒度调整材料配制的挖掘液在深厚砂 层和卵、砾石地层为主的地层中有良好的适应性. [关键词]地下工程;TRD工法;颗粒度;砂层;卵砾石层 [中图分类号]TU753 [文献标识码]A [文章编号]1002-8498(2015)13-0060-04 Digging Fluid Preparation Method and It's Application of TRD Method in Deep Sand and Gravel Layer Chu Liqiang Shanghai Zhiping Foundation Engineering Co.Ld.Shanghai 200060 China) Abstract:Digging fluid prepared by bentonite is used for TRD method in cohesive soil and silty soil.The improved method is more suitable for sand and gravel layer.Based on engineering practice this paper mainly introduced calculation method of digging fluid preparation using cohesive soil instead of bentonite. Engineering practice shows that this improved digging fluid is suitable for TRD method in deep sand and gravel layer. Key words:underground;TRD method;granularity;sand layer;gravel layer 0引言 侧为长江,本工程地下室边线距离长江堤岸最近处 武汉长江航运中心大厦暨民生路长航小区扩 仅约60m 已经进入堤防保护线5~6.5m. 建工程基坑围护采用地下连续墙和TRD工法止水 沿江大道下分布有电力、光纤、电信、路灯、给 帷幕,基坑开挖深度18.9~22m 局部开挖深度排水等管线.红线内场地西北侧分布1幢14~16 28.9m.本工程地层中含砂量较大,其中纯细砂(铁 层保留居民楼,距离本工程地下室10~14m 在基坑 板砂)层厚度约20m 中细砂夹卵砾层厚度3~4m、1倍开挖深度范围内,采用的预制桩桩端标高 其余地层内含砂量亦较大.参考国内外相关施工7.400m(相对本工程±0.000为-18.700m) 本工 经验,采用了以优质黏性土代替膨润土的挖掘液配 程基坑普遍开挖深度-18.300m 开挖面位于其桩 制形式,改善了挖掘液悬浮砂颗粒的性能,减小了 端以上400mm. 施工推进的阻力,取得了较好的效果. 2工程地质条件 1工程概况 地...