2011年7月上 施工技术 第40卷第344期 CONSTRUCTION TECHNOLOGY 75 砂卵石地层中钻孔灌注桩成孔控制技术 王俊利,刘会林 (中国铁建十六局集团有限公司,北京100124) [摘要]在砂卵石地层采用钻孔灌注桩成孔难度较大.以北京地铁十号线某盾构始发井围护桩施工为例,对在砂 卵石地层中影响钻孔柱成孔效率和质量的主要原因进行了分析,并针对设备选型和泥浆护壁两方面对成孔质量控 制措施进行了闸述.根据不同的地质条件选择适合的成孔钻具和泥浆参数,保证了成孔质量,提高了施工效率. [关键词]钻孔灌注桩;砂卵石地层:旋挖钻机;短螺旋钻头 [中图分类号]TU753.3 [文献标识码]A [文章编号]1002-8498(2011)13-0075-02 Pore-forming Control Technology of Bored Pile in Cobble Stratum Wang Junli Liu Huilin (China Railway 16th Bureau Group Co.Ltd.Beijing 100124 China) Abstract:It is difficult for pore-forming with bored pile in cobble stratum.Based on retaining pile construction of shield-construction origination shaft in Beijing Subway line 10 authors make analysis on the main cause of influence on efficiency and quality of pore-forming with bored pile in cobble stratum and expound quality control measures from equipment selection and mud protection.They choose the suitable drilling tool and mud parameters which ensure pore-forming quality and improve construction efficiency. Key words:bored pile;cobble stratum;rotary drilling rig;short screw auger 1工程概况 盾构始发井所处地层由上至下分别为:人工填 北京地铁十号线二期西局站~六里桥站区间1土层、第四系新近沉积层、第四系沉积土,其中第四 号、2号盾构始发井均为单跨3层钢筋混凝土矩形系沉积土中的⑤卵石层(厚10.7m)、⑦卵石层(厚 结构.两始发井结构形式及尺寸完全相同,盾构始8.9m)、⑨卵石层(厚7.8m)、①砾岩层(未见底), 发井内净空尺寸为14.7m×8.7m 基坑开挖深度为 地层中卵石粒径较大,最大粒径40cm 直径>20cm 26.59m 采用钻孔灌注桩钢支撑钢围檩围护结 的颗粒物含量约为70%,工程地质条件差,对钻孔 构,钻孔灌注桩桩径1000mm 桩间距为1400 灌注桩施工影响较大. (1500)mm 桩长为34(35)m 桩底深入结构底板面 2.2水文地质条件 以下8.921m;桩顶设1000mmx800mm冠梁,冠梁 根据区域水文地质资料,本段线路赋存4层地 上设1500mm×200mm挡水墙. 下水...