施工技术 2015年12月下 98 CONSTRUCTION TECHNOLOGY 第44卷第24期 D0I:10.7672/sgjs2015240098 钢构件预拼装在大桁架工程中的应用 孙学红 (中铁建设集团有限公司北京分公司,北京100040) [摘要]结合北京市丰台区丽泽路长城金融工程项目的大桁架预拼装实例,着重介绍了钢结构预拼装的技术流程 以及在工程施工中的重要性,如此提高钢结构现场焊接的合格率,既保证了施工安全、节约了材料,又提高了劳动 生产率、减少了施工费用,同时缩短了工期. 【关键词]钢结构;桁架;预拼装;施工技术 [中图分类号]TU758.11 [文献标识码]A [文章编号]1002-8498(2015)24-0098-03 Application of Steel Members Pre-assembly in Large Truss Construction Sun Xuehong Beijing Branch of China Railway Construction Group Co.Ltd.Beijing 100040 China) Abstract:Based on large truss pre-assembly construction of Great Wall Finance project in Fengtai district of Beijing this paper introduces the technical process of steel structure pre-assembly and importance in construction the pre-assembly technology improves the qualified rate with site welding for steel structure ensures construction safety saves materials improves labor productivity saves construction cost shortens construction period. Key words:steel structures;trusses;pre-assembly;construction 1工程实例 施工完毕,确保施工过程中万无一失,特要求钢结 本工程位于北京西二、三环之间的丽泽金融商 构大桁架构件必须加工完毕后在加工厂进行 务区,塔楼建筑总高度154m 共33层,地下4层.预拼装,预拼装完成后经四方检查、验收合格后方 主楼结构形式为型钢混凝土框架剪力墙核心筒 可进入现场.钢结构大桁架预拼装方案采用 结构.本工程在①/③~⑧轴设置转换钢桁架,桁Autodesk CAD软件进行放样,进行严格尺寸标注, 架层为5~7层,桁架杆件最大截面L1(2×H900× 对钢构件拼装后经过现场测量数据记录,将测量数 900×80×80) 材质均为Q345B.单根梁弦杆长度 据输人计算机后与原设计进行对比,检查加工构件 达29.7m 分别为上、中、下弦,单钢构件最重达32t. 是否满足设计要求,最后对整体钢结构大桁架验收. 经过前期的钢结构深化设计,将大桁架分解为27段 3.1预拼装方法的确定 吊装,安装接口为40道,安装焊缝约150条,吊装总 预拼装方法分为以下4种:①整体预拼法将 质量约440t. 需要进行预拼装范围内的全部构件按施工详图所 2试装目的 示的平面(空间)位置,在工厂(现场)借...