2016年10月上 施工技术 第45卷第19期 CONSTRUCTION TECHNOLOGY 13 D0I:10.7672/5j52016190013 不封闭内支撑体系在软土深基坑中的应用 高雁,谢弘帅2,张亚为2 (1.台州职业技术学院建筑工程学院,浙江台州318000; 2.上海林同炎李国豪土建工程咨询有限公司.上海200092) [摘要]不封闭内支撑体系作为一种特殊支撑体系,其围护桩不连续且支撑体系上土压力不平衡.结合实际工程, 分析了不封闭内支撑体系在设计和施工过程中遇到的不利情况,提出了解决思路和技术措施,取得了良好的应用 效果. [关键词]深基坑;软土;支护;施工技术 [中图分类号]TU753 [文献标识码]A [文章编号]1002-8498(2016)19-0013-03 Application of Opening Support System of Deep Foundation Excavation in Soft Soil Gao Yan' Xie Hongshuai Zhang Yawei? (1.Department of Architecture Taizhou Vocational Technical College Taizhou Zhejiang 318000 China; 2.Lin Tung-Yen Li Guo-Hao Consultants Shanghai Lid.Shanghai 200092 China) Abstract:Opening support system is a special support system retaining pile discontinuity and the earth pressure on supporting system is imbalance.Combined with the actual cases this paper analyzed the adverse conditions of opening support system in the process of design and construction proposed the ideas and technique measures which obtained good effect. Key words:deep foundation excavation;soft soil;supports;construction 0引言 项目位于浙江省温岭市,工程地下室北侧为地 在东南沿海软土广泛分布的地区,由于软土的下1层,南侧为地下2层.±0.000处标高相当于 物理力学性质很差,基坑支护设计和施工难度较黄海高程5.600m 自然地坪为黄海高程 大.另外,由于用地空间狭小、周边环境复杂以 3.500m.地下1层底板垫层底设计标高为 及多种基坑开挖深度进一步增加了基坑设计和施 -5.750m 承台垫层底标高为-6.450m 开挖深度 工难度. 为3.65~4.45m.地下2层底板垫层底设计标高为 本文以浙江省温岭市某深基坑支护工程为研 -9.650m 开挖深度为7.55m 场地平面布置如图1 究对象,该基坑一半为地下1层,一半为地下2层, 所示. 两者高差4.40m.针对本工程特点,设计采用先开 2工程地质与水文地质条件 挖地下1层,后开挖地下2层的“先浅后深”的施工 2.1工程地质条件 顺序,且地下2层采用不封闭的支撑体系进行支护. 根据地质勘察报告,土层自上而下分布如表1 ...