施工技术 2013年8月下 50 CONSTRUCTIONTECHNOLOGY 第42卷第16期 DOI:10.7672/sgjs2013160050 大体量建筑大位移整体顶升技术 李国雄 (广州市鲁班建筑集团有限公司,广东广州501665) [摘要]结合济宁贵和购物中心整体顶升工程和某高层建筑顶升纠偏工程,介绍了建筑物大位移顶升工程中的托 换结构、顶升设备以及顶升稳定性和同步性的控制。
结合深圳某高层建筑顶升纠倾工程,介绍了大体量建筑物顶 升纠倾工程中的基础加固、设计施工方法以及施工中出现的问题,并提出相应的处理措施和注意事项。
[关键词]加固;顶升;托换;纠倾 [中图分类号]TU746.4 [文献标识码]A [文章编号]1002-8498(2013)16-0050-04 Application ofLarge-displacementIntegralLifting TechnologyinLarge-scaleBuilding Li Guoxiong (Guangzhou Luban Construction Group,Guangzhou,Guangdong 501665,China) Abstract;Combined with engineering practice of the integral lifting project of Ji'ning Guihe Shopping Center and the lifting andrectification ofa tallbuilding,the underpinning structure,lifting equipments, Combined with engineering practice of anintegral lifing project in Shenzhen,foundation reinforcement, design and construction methods,and construction experience were introduced in the lifting project with big volume, the corresponding measures and attention points are provided. Key words:strengthening;lifting;underpinning;rectification 顶升技术在建筑物及构筑物整体移位工程中1.2工程特点 得到广泛应用,如建筑物整体平移工程中平移换向 本工程需要顶升的位移为1.8m,如此大位移顶 倾斜后的纠倾顶升,桥梁安装时箱形梁的顶升,桥 对顶升稳定性和准确性要求较高,施工过程中保证 梁坡度改变时的顶升等。
顶升前需对原结构进行 不偏位的难度较大。
建筑物需顶升部分的建筑面 可靠托换,顶升过程需保证顶升的同步性及稳定 积约4000m²,首层面积约1000m²,框架柱间跨度 性,特别对于顶升位移较大或者建筑物体量较大的 为7.2m,对于大面积和大跨度建筑的整体顶升,顶 顶升工程,更要予以重视。
升过程中建筑物整体性的协调和整体抬升同步性 1济宁贵和购物中心整体顶升工程 均要求较高,细微的误差极易造成建筑物的局部开 1.1工程概况 裂。
通过计算可知顶升时单柱最大轴力约为 济宁贵和购物中心为4层大型商场,建于20世 4000kN,大吨位的轴力需要使用大吨位的千斤顶提 纪90年代,结构形式为框架结构,基础形式为桩基 供足够的顶升力,同时原有结构构件的保护也尤为 础。
该建筑首层为错层构造,首层①-~①-D轴 重要,避免造成构件的局部破坏。
间区域标高低于该层其他区域,标高相差1.76m。
1.3顶升的托换底盘 由于使用功能要求需改变错层构造,将二层楼面全 建筑物重约8000t,整体上升必须将建筑物的 部做平,故需将标高下沉部分整体顶升。
此外,顶 全部柱子从底部截断,因此需要制作1个牢固稳定 升后首层层高较大,业主要求在首层再做1个夹层。
的托换底盘先将建筑物托住,然后才能截断柱子。
[作者简介]李国雄,董事长,高级工程师,E-mail:Ib_lgx@163. 采用混凝土包柱式托换形式,每根框架柱被钢筋混 [收稿日期]2013-04-13 凝土包裹托换后形成顶升承台,包柱式承台与原柱 万方数据
2013 No.16 李国雄:大体量建筑大位移整体顶升技术 51 形心重合,承台之间均设置连系钢梁及交叉斜撑, 方式(见图3)。
在平面内形成具有一定刚度的几何不变体系,这种 加大截面纵筋 加大截面纵筋 开原梁 避开原梁 结构既能将各根柱子承托起来又能使其相互之间 400 拉接连系在一起,对提...