施工技术 2016年7月上 28 CONSTRUCTION TECHNOLOGY 第45卷第13期 D01:10.7672/js2016130028 超深块石回填地质条件下超长桩施工技术 胡刚,李欢,康鑫,彭先奇 (中天建设集团有限公司,浙江杭州310008) [摘要]依托重庆中航MyTown工程,针对超深中风化块石回填土质条件下超深钻孔灌注桩施工难题,通过对旋挖 钻机、钻头、钢护筒拼接等的改进优化,采用全回转钻机协同旋挖钻机、全钢护筒跟进施工技术,解决了回填地质条 件下40~80m柱的成孔、成桩技术难题. [关键词]桩基础;钻孔灌注桩;钢护筒;回填土:施工技术 [中图分类号]TU753.3 [文献标识码]A [文章编号]1002-8498(2016)13-0028-03 Construction Technology of Extra-long Bored Piles in Extra-deep Block Stone Filling Stratum Hu Gang Li Huan Kang Xin Peng Xianqi (Zhongtian Construction Group Co.Lad.Hangzhou Zhejiang 310008 China) Abstract:Based on Chongqing Zhonghang MyTown building project in view of the construction problems of extra-long bored piles in extra-deep block medium weathered stone filling stratum through the improvement of rotating drill bit and steel casing using the full-circle boring machine with auger drill work together and the technology of steel casing which solved the hard technological problem of 40 ~80 m pile in extra-deep block stone filling stratum. Key words:piles;bored piles;steel casing;back-filing;construction 1工程概况 土层渗透系数大,无法进行泥浆护壁,需采用干法 中航MyTown工程项目位于重庆市渝北区,地作业,且土层稳定性差,孔壁的稳定性难以保证,清 下1层,地上14~16层,6幢主楼,建筑面积约18 孔困难,选用合理的护壁措施是保证孔壁稳定的关 万m2.工程所处原地貌为1条深沟,上宽约80m 键技术. 深度约85m 剖面形状呈倒三角形,后采用周边开挖 3)土层块石含量大,且上部回填段存在大粒径 后的土石方进行回填,以中风化为主,最深处达 孤石,桩基施工时易引起钻进不进尺、孔倾斜偏移、 68.8m 经3年的沉降期.工程采用钻孔灌注桩基 发生卡钻等问题. 础,桩基共1105根,设计直径为1.0 1.2 1.5m 桩 4)块石回填地质条件下,旋挖过程中钻头的磨 长17~73m 其中超过40m的桩有333根,60m以上 损率较高,钻齿更换的频率对施工效率影响很大, 的有56根,均需穿过块石回填土层进入基岩持 合理优化钻头、降低钻头磨损率、提高破岩效率对 力层. 成本控制和工...