2013年5月下 施工技术 第42卷第10期 CONSTRUCTION TECHNOLOGY 105 D0I:10.7672/sgjs2013100105 异步距异节奏流水施工组织方法研究* 郑显春,李志强,李鹏飞 (河北建筑工程学院土木工程学院,河北张家口075024) [摘要]首先介绍了异步距异节奏流水施工的特点,提出多个施工层异步距异节奏流水施工的组织方法,得到流水 施工工期计算公式,并通过3个具体实例加以详细说明,对《工程项目组织与管理》、《土木工程施工组织》等课程 建设起到一定的促进作用. [关键词]项目管理,流水施工,异步距,异节奏,组织方法 [中图分类号]TU71 [文献标识码]A [文章编号]1002-8498(2013)10-0105-03 Research on Flow Construction Organization Method with Different Pace and Different Rhythm Zheng Xianchun Li Zhiqiang Li Pengfei (School of Civil Engineering Hebei University of Architecture Zhangjiakou Hebei 075024 China) Abstract:The characteristics of flow construction with different pace and different rhythm are firstly introduced.An organization method was proposed which allows multiple floors to be constructed in flow construction with different pace and different rhythm and the equation was provided to calculate the construction period.Its application was illustrated in detail with three examples.This work helps to improve the courses of construction organization and management construction organization for civil engineering etc. Key words:project management;different pace;flow construction;different rhythm construction;organization 0引言 1异步距异节奏流水施工特点 按照流水节拍的特征,流水施工方式可分为等 施工特点包括:①同一施工过程在各个施工段 节奏流水、等步距异节奏流水、异步距异节奏流水 上的流水节拍均相等;②不同施工过程之间的流水 及无节奏流水施工4种.在实际工程中,往往由于 节拍不完全相等,也不存在倍数关系;③流水步距 各方面的原因,如工程性质、复杂程度、劳动量、技 不完全相等;④专业工作队数等于施工过程数(即 术组织等,采用相同的流水节拍来组织施工是不可 每个施工过程只安排一个专业工作队). 能的.此时便可采用异步距异节奏流水施工的组2异步距异节奏流水施工的组织方法 织形式来组织施工. 单个施工层异步距异节奏流水施工的组织方 以往的文献...
推荐内容/By 图集吧
- 物流园受煤工程施工组织设计.doc
- 地下综合管廊项目防水工程施工方案.doc
- 泰国酒店EPC施工组织设计技术标(含支护及土方)264页.docx
- DB11/T 2292-2024 市政工程施工组织设计管理规程.pdf
- 【word版、可编辑】光伏发电项目施工设备安装技术方案整理汇编(253页).docx
- 徐州办公楼扩建中央空调、通风工程施工组织设计.doc
- 中建智能快递物流中心装饰装修施工组织设计(400页、2023年编制).docx
- 消防水池、化粪池基坑土方开挖、支护、降水施工方案-八局青岛-山东大学齐鲁医院妇儿综合楼一期工程.docx
- 中建八局水系综合整治工程安全文明与绿色施工方案(76页、word版、可编辑).doc
- 中建二局型钢悬挑脚手架专项施工方案编制模型 2023年6月版(含cad图).zip
- 长阳半岛装配整体式剪力墙结构施工组织设计.pdf
- 岩溶地质旋挖灌注桩成孔工艺及其基桩质量控制研究.pdf